Execute Plan

Execute a plan in FlowWrightPM

Last published at: July 25th, 2024

Once the plan is developed, it can be executed. When executed, FlowWright engines analyze and execute the plan's design; the executed plan is created within the In-Progress tab of the UI. 

Select a plan and click the Execute button.  

 

The following UI is rendered for configuration. For the chosen plan, you will need to provide the Execution Name and DateTime value. Click on the Execute button to start.  

 

The plans in-progress are located in IN-PROGRESS tab as shown below. 

 

The plan is executed, and any open tasks are placed in the Open folder, as below. The Task page is focused on the Plan and lists all the Open tasks for all plan members using filters.